Microsoft Project vs SiteCal for construction scheduling

Microsoft Project is one of the most capable scheduling tools ever made. It was also built for every kind of project, not for builders. Here's an honest look at how the two compare on features, cost, sharing with trades and day-to-day use on site.

SiteCal versus Microsoft Project for construction scheduling
Key takeaways
  • 01Microsoft Project is the deeper tool. Resource and cost management, critical path, baselines and portfolio roadmaps suit large contractors and dedicated planners.
  • 02SiteCal is built for small and mid-sized builders who need a clear program, linked tasks that move when the job moves, and a live link they can send to every trade.
  • 03Cost works differently. Microsoft Project is priced per user. SiteCal is a flat monthly price by active jobs, with trades always free.

1. The short answer

If you run a planning department, manage resources and costs across a portfolio of large projects, and have people trained to drive it, Microsoft Project is hard to beat.

If you're a builder or site manager who needs to build a program quickly, keep it up to date when the job moves, and get it in front of your trades without emailing PDFs, SiteCal does that job with far less overhead and usually at a lower cost. It’s a Microsoft Project alternative built just for construction — focused on the program, not a whole project-management suite.

SiteCal
Best for
  • Residential and small commercial builders
  • Site managers who run the program themselves
  • Teams that share the program with lots of trades
Microsoft Project
Best for
  • Large contractors with dedicated planners
  • Resource levelling and cost-loaded schedules
  • Organisations already standardised on Microsoft 365

2. What each tool is built for

Microsoft Project is general-purpose project management software. The same tool plans software releases, marketing campaigns, IT rollouts and construction jobs. That's why it's so capable: dependency types with lead and lag, critical path, baselines, resource and cost management, and roadmaps across projects and portfolios. It's also why it can feel heavy for a builder. Most of what it can do, a residential job never needs.

Microsoft now sells it in two main ways. Planner Plan 1 is the browser-based option (formerly Project for the web). Planner and Project Plan 3 adds the Project desktop app, which runs on Windows only. You can also buy Project Professional 2024 outright as a one-off licence for a single PC.

SiteCal is construction scheduling software built by a Melbourne site manager for builders and site managers. It does one job: plan the work, sequence the trades and keep the program true as the job moves. You get a Gantt timeline and a month calendar of the same program, links that shift the whole chain when a task moves, trade colour-coding, progress and delay tracking, and a live link you can share with every trade and client.

Microsoft Project asks what your project is. SiteCal already knows: it's a build, and the trades need to know when to turn up.

3. Feature comparison

A side-by-side look at what matters when you're running jobs. Ticks mean the feature is there and does the job well. Half marks mean it's possible, but it takes extra work or a workaround.

Feature
SiteCal
Microsoft Project
Planning
Gantt timeline
✓Yes
✓Yes
Calendar view of the job
✓Month calendar, one click from the Gantt
✓Calendar view
Linked tasks
✓Move one task, shift the whole chain with it
✓Full dependency types with lead and lag
Critical path and baselines
~Days ahead or behind on every job
✓Yes, in depth
Resource and cost management
–Not included, scheduling only
✓Yes
Built for construction
Trade colour-coding
✓Every trade gets its own colour
~Manual bar formatting
Made for builders
✓Built by a site manager
–General project management
Sharing and access
Share with trades
✓Live link, no login or paid seat
~Usually a PDF export, or a paid licence each
Use it on a phone on site
✓Works in the browser on phone, tablet and desktop
~Lighter Planner view; full desktop app is Windows only
Works on a Mac
✓Any browser
–No Mac desktop app
Cost and commitment
Pricing model
✓Flat monthly by active jobs, from $89 inc GST
~Per user, from AU$15 ex GST a month
Commitment
✓Month to month
~Listed plans are paid yearly
Free trial
✓14 days, no credit card
~Varies by plan

4. What it actually costs

The biggest difference isn't the sticker price. It's what you pay for. Microsoft Project charges for every person who needs to work in the schedule. SiteCal charges by how many jobs you're running, includes your team's seats in the plan, and never charges for trades.

PlanHow it's pricedListed priceInc GST
SiteCal Starter
5 active jobs, 10 seats
Flat, month to month$89/mo$89/mo
SiteCal Builder
20 active jobs, 30 seats
Flat, month to month$109/mo$109/mo
SiteCal Pro
Unlimited
Flat, month to month$199/mo$199/mo
Planner Plan 1
Browser only
Per user, paid yearly$15.00/user/mo$16.50/user/mo
Planner and Project Plan 3
Includes the desktop app
Per user, paid yearly$44.90/user/mo$49.39/user/mo
Project Professional 2024
One PC, no subscription
One-off licence$2,299$2,299

All prices in AUD. Microsoft lists its subscription plan prices excluding GST; we've added 10% so they compare like for like with SiteCal, which is GST-inclusive. Project Professional 2024 is Microsoft's Australian Store price for a one-off licence (GST inclusive). Prices checked October 2026.

Monthly cost as your team grows
Inc GST, by the number of people who need to work in the program. Trades not included, because on SiteCal they're free.
SiteCal Planner and Project Plan 3 Planner Plan 1 (browser only)
View as table
PeopleSiteCalPlan 3Plan 1
Assumes your active jobs fit the SiteCal plan: up to 5 on Starter, up to 20 on Builder.

The pattern is simple. Microsoft Project's cost climbs with every person you add. SiteCal's stays flat until you outgrow a plan. With two people using Plan 3, you're already paying more than SiteCal Starter. With ten, Plan 3 costs more than five times as much.

To be fair: Microsoft's browser-only Planner Plan 1 is cheaper for very small teams, up to five people. It doesn't include the Project desktop app, though, and trades without a licence still can't work from the live plan.

First-year cost for a typical builder
A team of 6 (office and site) running 8 jobs at once. Inc GST.
View as table
OptionFirst year
SiteCal Builder ($109 × 12). Plan 1 and Plan 3: 6 users × 12 months. Project Professional 2024: 6 one-off licences, one per PC.

5. Getting the program to your trades

A program only works if the people doing the work can see it. This is where the two tools differ most for a builder.

In Microsoft Project, the schedule lives with whoever has a licence. Your plumber, sparky and plasterer won't have one, so they usually get a PDF or a printout. The moment something moves, that PDF is out of date, and you're sending another one.

In SiteCal, every trade and client gets a live link to the program. There's no login and no paid seat. When you move a task, they see the change.

Microsoft Project 5 STEPS
  1. Open the scheduleUsually on the office PC, in the desktop app.
  2. Push the task out three daysCheck the linked tasks moved the way you expected.
  3. Export a new PDFPrint or save the updated version.
  4. Email every tradeAnd hope they open the latest attachment.
  5. Field the phone callsFrom trades working off last week's copy.
Result: several versions of the program in circulation.
SiteCal 2 STEPS
  1. Move the taskFrom your phone on site or your laptop in the office.
  2. Shift the linked tasks with itEvery trade's link already shows the new dates.
Result: one program, always current, for everyone.

Example: a three-day rain delay on the frame, with trades following on behind.

6. Using it on site

Most program changes happen on site, not at a desk. The full Microsoft Project desktop app runs on Windows only, and there's no Mac version. Microsoft's Planner gives you a lighter view in the browser, in Teams and on mobile, but the detailed scheduling lives in the desktop app.

SiteCal runs in the browser on a phone, tablet or computer. Check what's on this week, flip to the month calendar, or move a task the moment you find out the frame's running late, without waiting until you're back in the office.

7. Setup and learning curve

Microsoft Project is powerful, and the price of that power is complexity. Getting real value from it usually means learning task types, constraint types, calendars and views, and many teams send people on a course to do it. In a lot of building companies, one person ends up owning the schedule because they're the only one who knows how it works.

SiteCal is designed to be learned in an afternoon. Add your stages and tasks, link them, colour them by trade, and share the link. There's less to configure, because it only does what a builder needs.

8. Where Microsoft Project is the better choice

SiteCal isn't the right tool for everyone. Microsoft Project is the better fit if:

  • You need resource levelling or cost-loaded schedules. SiteCal is a scheduling tool and doesn't try to manage labour hours or budgets.
  • Your contracts or clients require it. Some head contracts and government projects specify a native Microsoft Project file.
  • You run large, complex projects with a dedicated planner. Thousands of tasks, detailed critical path analysis and formal baseline reporting are what Microsoft Project was built for.
  • You manage a portfolio. Plan 3 adds portfolio tracking across multiple projects.

9. The verdict

Choose SiteCal if…

  • You run residential or small commercial jobs
  • You (or your site managers) build the program yourselves
  • You want trades working from a live program, not a PDF
  • You'd rather pay by jobs than by seats, month to month

Choose Microsoft Project if…

  • You have a dedicated planning team
  • You need resources, costs and baselines in one schedule
  • A contract specifies Microsoft Project files
  • Your business is standardised on Microsoft 365

For most builders, the job of a program is simple: show everyone what's happening and when, and stay right when things change. That's the job SiteCal was built for.

10. Frequently asked questions

Is SiteCal a replacement for Microsoft Project?+
For most residential and small commercial builders, yes. SiteCal covers building the program, linking tasks, tracking delays and sharing with trades. If you rely on resource levelling, cost loading or portfolio reporting, Microsoft Project does more.
Is Microsoft Project good for construction scheduling?+
It can be — it is genuinely powerful at scheduling, with critical path, baselines and resource management. But it is general-purpose software with a steep learning curve, the full desktop app is Windows only, and trades cannot see the program without a paid licence. For most residential and small commercial builders, a construction-specific tool is faster to run day to day.
How much does Microsoft Project cost in Australia?+
Microsoft lists Planner Plan 1 at AU$15.00 per user per month and Planner and Project Plan 3, which includes the desktop app, at AU$44.90 per user per month. Both are paid yearly and exclude GST. Project Professional 2024 is a one-off licence for one PC, AU$2,299 on the Microsoft Store.
Do my trades need a licence to see the program?+
On SiteCal, no. Trades and clients open a live link without logging in or paying for a seat. With Microsoft Project, anyone without a licence usually gets an exported PDF instead.
Does Microsoft Project work on a Mac?+
The Project desktop app is Windows only. Mac users can use Microsoft Planner in the browser, or run Windows on their Mac. SiteCal works in any browser, on Mac, Windows, tablet or phone.
Can I use SiteCal on my phone?+
Yes. SiteCal works in the browser on desktop, tablet and phone, so you can check and update the program on site.
Is Microsoft Project being discontinued?+
Project Online, Microsoft’s older cloud product, was retired on 30 September 2026. Microsoft still sells the Project desktop app through Planner and Project Plan 3, and the browser-based Planner plans.
How do I try SiteCal?+
Every plan starts with a 14-day free trial, with no credit card required. Build the program for your next job and share it with a couple of trades to see how it works.